Hi Arijit,
Thanks for your reply.
The data we are getting in report after applying report filter Cumulative of Percentage <=0.8 but still it showing above 80% record is as below
Cumulative of Percentage =runingsum (Percentage;(Custid))
Custid | Project | Kf | Percentage | Cumulative of Percentage |
1 | 201 | 10 | 7.69% | 7.69% |
1 | 202 | 30 | 23.08% | 30.77% |
1 | 205 | 40 | 30.77% | 61.54% |
1 | 102 | 50 | 38.46% | 100.00% |
2 | 203 | 50 | 14.29% | 14.29% |
2 | 206 | 100 | 28.57% | 42.86% |
2 | 208 | 200 | 57.14% | 100.00% |
And expected output is
Custid | Project | Kf | Percentage | Cumulative of Percentage |
1 | 201 | 10 | 7.69% | 7.69% |
1 | 202 | 30 | 23.08% | 30.77% |
1 | 205 | 40 | 30.77% | 61.54% |
2 | 203 | 50 | 14.29% | 14.29% |
2 | 206 | 100 | 28.57% | 42.86% |
Thanks & Regards,
Anish