Hi Alice,
MD41 is relevant for MPS run.
Please check if these new materials are relevant for MPS (ref MRP type in Material master = M0 or so)
Can you please confirm the following?
a) The newly added items are not 'Bulk' or 'Phantom' items; but they are in fact 'Stock' items.
b) Reservations for the new additions show up - from the Production order
c) MRP type for the newly items are relevant for MRP (say PD or so); or MPS (M0 or so)
- If MRP,... please use MD03/MD02/MD01 for MRP run and check the results
- If MPS,... please use MD41/MD42/MD40 for MPS run and check the results
Thanks
Senthil