Hi Jeffrey, There is the Activity Type field in the Work Order confirmation in the Work Manager app, but if you wanted to split across multiple Activity Types using the standard application you could use the Operations to split time and activity type across the Work Order. Even if the WO had only one operation the field tech could use standard functionality to add additional operations as required.
↧