Hi
Have got below issue.
Thru MRP run for procurred items system is creating planned order instead of purchase requistions even though all system & master data settings are set properly.
Master data settings:
MRP Type: VB(just mentioning this as for PD materials this issue is not observed)
Scheduling Margin key: 000 - float period is 0
Procurement type: F
Special procurement type: blank
Source list maintained with fixed vendor
MRP job parameters:
Creation of PR: 2- PR's in opening period
Even though above setting is chosen in my view system should create PR as the scheduling margin key is 000 (with zero opening period)
Does any one came across this issue?
BR,
Ragahva