Consideration of stock of discontinued FG or trading material during MRP Run

$
0
0

There is an functionality of follow up material for component. I would like to know if there is any similar option available for finished goods or trading materials.

I am doing procurement planning for externally procured Trading materials. Now my previous material A is being replaced by material B. Therefore all the planned independent requirement is available in system only for B. But still there is some stock available for material A. How can it be considered during MRP run for material B.


Example,

Material A:

On Hand Stock = 100

Planned Independent Req. = 0


Material B:

On Hand Stock = 300

Planned Independent Req. = 1000

 

In this case if we run MRP for material B, how we ask system to plan Purchase Requisitions for 600 instead of 700 for material B, considering stock of material A.